Valley Metro
Kiewit Infrastructure West Co.
AECOM
Hill International, Inc.

Project Description
Phoenix, California
The South Central Extension / Downtown Hub (SCE/DH) project expanded Valley Metro’s light rail system by 5.5 miles, connecting downtown Phoenix with South Phoenix through eight new stations and a multimodal Downtown Hub. Introducing Valley Metro’s first two-line operating system, the project improved transit frequency, reliability and regional connectivity while expanding access to jobs, education, healthcare and other opportunities for a historically underserved community.
Delivered using a Construction Manager at Risk (CMAR) model, the project involved extraordinary technical, political and community complexity. Construction required relocating or upgrading more than 220,000 linear feet of utilities, navigating densely developed neighborhoods and business districts, and coordinating more than 25,000 linear feet of monitored excavation that yielded 102,000 cultural artifacts. Further work entailed a 110-space park-and-ride facility, a new Salt River light rail bridge, 18 public art installations, extensive landscaping and major infrastructure upgrades.
Adding to the project’s complexity, the team faced unexpected utility conflicts, more than 20 COVID-19-related impacts and demanding construction windows, including blackout periods associated with Super Bowl LVII.
Despite these challenges, SCE/DH achieved substantial completion in April 2025 and opened to the public in June 2025, one year ahead of its federal grant schedule and under budget. A shared commitment to collaboration, proactive communication and a can-do approach to problem-solving was instrumental in overcoming obstacles and successfully delivering this mega-transit project to the Phoenix community.
Partnering Approach
With so many technical, political and community considerations converging along a single urban corridor, navigating these complexities depended on a unified team, proactive communication and a shared commitment to finding solutions.
Construction Partnering was implemented early-on to help establish a team environment grounded in shared goals, transparency, and mutual accountability. Working with VELO Group as a neutral facilitator, Valley Metro, the City of Phoenix, the CMAR team, designers, utilities, and other stakeholders were brought together in a structured setting to align expectations related to safety, schedule, cost, quality, and community impact.
Early partnering sessions created a common understanding of roles, responsibilities, and issue-resolution pathways. These relationships were reinforced throughout the project with recurring coordination meetings, facilitated partnering touchpoints, and consistent leadership engagement. By addressing challenges openly and collaboratively — rather than through contractual positions — the team built enduring trust through political uncertainty, archaeological discoveries, utility constraints, and schedule pressures.
When unexpected conditions arose, the team emphasized collective problem-solving rather than individual interests. A multi-day value engineering workshop conducted at just 15 percent design generated 197 ideas, 41 of which were implemented, resulting in more than $26 million in savings.
Through strong owner-contractor-manager relationships, a shared commitment to project success and a willingness to adapt, the team maintained momentum despite complex challenges and delivered a transformative public infrastructure project that will serve the traveling public for decades to come.
Partnering Results
- Opened one-year ahead of schedule
- Delivered under budget with $26 million in verified savings through value engineering
- Enhanced communication and teamwork among the project team and third-party stakeholders
- Safety record outperformed industry average over 4.8 million work hours
- Fostered innovation and creative problem-solving
- Improved quality and long-term value
- Issue resolution procedures mitigated any unresolved claims or legal proceedings
- Enhanced community relations, through collaboration with more than 270 corridor businesses and local tribal communities
- Recipient of 11 regional and national awards
Project Notes
- Project Cost: $980 million
- Delivery Method: Construction Manager at Risk
- Groundbreaking: 2019 Utility Work Began
- Substantial Completion: April 2025
- Public Opening: June 2025
Awards
2026 IPI John L. Martin Partnered Project of the Year
See more project awards